Scrapbook Photo 11/18/24 - 107 New Stories - REAL Environmental & Conservation Leadership In PA: http://tinyurl.com/3zb7jppr
DEP Reissues Draft Water Quality Permit For Brunner Island Power Plant In York County For Comment

The Department of Environmental Protection Friday announced it has reissued a revised draft National Pollutant Discharge Elimination System (NPDES) permit for the Brunner Island Power Plant in York County for the operation of its 1,490-megawatt coal- and natural gas-fired power plant, which discharges treated industrial wastewater and cooling water to the Susquehanna River.

“This is DEP’s fourth attempt to update Brunner Island’s discharge permit due to changing federal discharge guidelines,” said DEP Southcentral Regional Director Joe Adams. “While the plant continues to operate under the terms of its previous permit, it is long past time to update and finalize the terms of a new permit that will be in effect for the coming years.”

The revised draft permit addresses revisions to compliance dates and requires studies of any temperature-related impacts on the Susquehanna River due to its operation as a peaking facility.

It includes additional reporting requirements for changes in plant operations that could lead to dramatic changes in thermal discharges. Sudden temperature changes in the plant’s discharge channel have resulted in fish kills.

The draft permit also extends by two years dates to comply with effluent limits for certain wastewater streams.

The NPDES permit Brunner Island is currently operating under expired in 2011. In the interim, DEP has administratively extended the terms of that permit, and issued three draft permits, the most recent in April 2017. That draft was subject to a 30-day public comment period and a public hearing conducted on July 24, 2017.

Based on comments received, and changes made in September 2017 by the U.S. Environmental Protection Agency to its wastewater guidelines, DEP decided to re-draft the permit for a fourth time.

While EPA may ultimately decide to revoke, amend, or leave undisturbed the guidelines currently in effect, DEP must utilize them in NPDES permits in accordance with the Clean Water Act.

A notice of the revised draft permit will be published in the PA Bulletin on January 20, 2018 (page 530). That will begin a 30-day public comment period which ends on February 20, 2018. DEP will consider any comments received before deciding on whether to issue a final permit.

The draft permit is available for public review at the DEP Southcentral Regional Office, 909 Elmerton Avenue, Harrisburg, PA 17110, Monday through Friday between 8:00 a.m. and 4:00 p.m. Please call 717-705-4732 to schedule an appointment.

It can also be accessed on DEP’s Southcentral Regional Office webpage.  Questions should be directed to John Repetz at 717-705-4904 or send email to: jrepetz@pa.gov.

[Posted: Jan. 19, 2018]


1/22/2018

Go To Preceding Article     Go To Next Article

Return to This PA Environment Digest's Main Page