Chester County District Attorney Opens Criminal Investigation Into Mariner East Pipeline Construction
Photo

On December 19, Chester County District Attorney Thomas Hogan announced he has opened a criminal investigation into the construction and “not so subtle bullying” of residents in connection with Sunoco’s Mariner East Pipelines.

“In the last two years, we have seen these pipelines rip through the heart of Chester County. We have seen sinkholes created by the pipeline drilling, contaminated well water, and some subtle and not-so-subtle bullying of Chester County citizens by big corporate interests,” said District Attorney Hogan.  “We expected the state regulators and the governor to step in and assure the safety of Pennsylvanians. They have not. So now the Chester County District Attorney’s Office will demand that every aspect of these pipelines be conducted safely, or we will bring into play all of the tools of the criminal justice system.”

The Mariner East 1, 2, and 2X pipelines are intended to ship volatile natural gas from western Pennsylvania all the way to Marcus Hook in Delaware County, Pennsylvania.

These pipelines cut directly through the middle of Chester County, bisecting heavily populated residential areas, running near schools and businesses, and in close proximity to railroads and streets.

The Mariner East 1 pipeline previously existed to ship refined petroleum under Chester County running from the eastern portion of Pennsylvania to the west.

Refined petroleum is a very different substance than natural gas and Mariner East 1 is smaller than the planned Mariner East 2 and 2X pipelines. Sunoco intended to build the Mariner East 2 and 2X pipelines along the same route as Mariner East 1.

In order to accomplish this, they intended to use horizontal directional drilling, a process that can be problematic depending on the area where drilling is occurring. Sunoco also introduced plans to reverse the flow of Mariner East 1 and use it to ship natural gas under Chester County in the older and smaller pipeline.

The Mariner East pipeline construction has experienced significant problems. On the property of homes in West Whiteland Township, the drilling resulted in significant sinkholes in the residents’ back-yards.

In another area of Chester County, the drilling caused the apparent contamination of well water for multiple residences. In Beaver County, Pennsylvania, there was an explosion along a pipeline, destroying a home.

The Department of Environmental Protection has fined the owners of the pipelines. But the construction of these pipelines keeps continuing.

“Two things recently happened that drew the attention of the District Attorney’s Office,” Hogan added. “First, the explosion in Beaver County changed speculation into tangible danger and destruction. Second, over Thanksgiving, some of the residents of Lisa Drive in West Whiteland were kind enough to take me onto their property and show me the damage caused by the pipelines. The concerns and fears of those citizens were both disturbing and heart- wrenching. I then detailed District Attorney staff members to do the legal research to make sure that the DAO had jurisdiction to investigate the pipelines and received an affirmative response.”

The District Attorney’s investigation will cover both past and future conduct related to the pipelines.

Potential charges include causing or risking a catastrophe, criminal mischief, environmental crimes, and corrupt organizations. Such offenses could include criminal charges directly against the individual employees involved, from workers on the pipelines through corporate officers.

Sunoco has been advised of this investigation via a letter.

“This investigation will not be easy. It will take time to dig into the historical information and we will need to constantly monitor any future activity. But we are committed to protecting Chester County. And we will need our citizens to help,” said Hogan.

Citizens Asked To Call

Chester County Detective Ben Martin is the lead investigator. The assigned prosecutors are Alexander Gosfield and Myles Matteson. Anybody with information should contact Detective Martin at 610-344-6866.

“We understand that only the Pennsylvania Utility Commission or the governor can shut down construction of these pipelines, and neither has shown any inclination to do so. But we can at least make sure that anything that happens in Chester County complies with the criminal laws of Pennsylvania. We owe that to our citizens. Money should not be allowed to trump safety,” said Hogan.

Click Here for more information on DEP’s actions related to the Mariner East 2 Pipeline.

NewsClips:

AP-Levy: Chester DA Begins Investigating Mariner East Pipeline Work

Hurdle: Chester County DA Opens Criminal Investigation Into Mariner East Pipelines

Crable: Chester County DA Opens Criminal Investigation Into Mariner East Pipelines

Chester County DA To Investigate Mariner East Pipeline Companies

Maykuth: Chester DA Launches Criminal Probe Into Mariner East Pipeline

Litvak: Prosecutor, Citing Beaver County Explosion, Begins Investigating Mariner East Pipeline Work

Chesco DA Launches Criminal Investigation Of Mariner East 2 Pipeline

Hurdle: PUC Investigators: We Didn’t Say Mariner East 2 Pipeline Was Safe

Hurdle: PUC Investigators Sees Statewide Concern With Mariner East 1 Pipeline Corrosion

Cong. Fitzpatrick, Rep. Staats  Ask For Planned Adelphia Pipeline Compressor Station To Be Moved

DEP Approves Shell Falcon Ethane Pipeline Project Permits

DEP OKs Shell Pipeline Permits Linking To Natural Gas Processing Plant In Washington County

Frazier: DEP Approves Pipeline To Shell’s Ethane Plant In Beaver County

Legere: Pipeline To Shell’s Ethane Plant Gets OK From DEP

Game Commission, Conservation Fund Atlantic Sunrise Pipeline Partnership Conserves 752 Acres In Sullivan County

Judge: PennEast Pipeline Can Use Eminent Domain In New Jersey

Federal Court Cites Dr. Seuss’s The Lorax In Rebuke To U.S. Forest Service As It Tosses Out Pipeline Permit

Related Stories:

PUC Enforcement Bureau Proposes $225,000 Penalty For 2017 Ethane/Propane Leak From Mariner East 1 Pipeline In Berks County

DEP Inspections Find Unreported Landslides On Right-Of-Way Of Newly Constructed Revolution Pipeline In Western PA, Compliance Order Issued

Delaware, Chester Citizens Group Releases Final Risk Assessment Report On Mariner East Pipelines

DEP Issues Modified Permits For Mariner East 2 Pipeline In Chester County; PUC Lifts Construction Ban At 2 Locations

DEP Assesses $148,000 Penalty Against Mariner East 2 Pipeline For Violations in Berks, Chester, Lebanon Counties

PUC Lifts Shutdown Order On Mariner East 1 Pipeline; Mariner East 2, 2x Pipeline Construction Remains Shut Down In Chester County

Sunoco Mariner East 2 Pipeline Fined $12.6 Million, DEP Allows Construction To Resume

Related Stories This Week:

Chester County District Attorney Opens Criminal Investigation Into Mariner East Pipeline Construction

2 Natural Gas Power Plants Beginning Operations In Westmoreland, York Counties Have Combined Generating Capacity Of 1.7 Gigawatts

DEP Invites Comments On Water Quality Certification For Proposed UGI Liquefied Natural Gas Truck Loading Facility In Berks County

Report: Investment In Natural Gas Pipelines, Infrastructure To Remain Strong Through 2035

[Posted: Dec. 19, 2018]


12/24/2018

Go To Preceding Article     Go To Next Article

Return to This PA Environment Digest's Main Page