Scrapbook Photo 03/25/24 - 93 New Stories - REAL Environmental & Conservation Leadership In PA: http://tinyurl.com/3729bhvv
Court: Injection Well Developer Does Not Need To Wait To Challenge A Local Zoning Decision Until It Has Permits For The Well

On March 8, Commonwealth Court issued a ruling that Penneco Environmental Solutions, LLC did not have to wait until it had state and federal permits in hand for a proposed drilling waste injection disposal well before challenging a ruling by Plum Borough’s Zoning Hearing Board against its project in Allegheny County.

Click Here for a copy of the ruling.

Related Story:

Commonwealth Court Clears The Way For Attorney General To Pursue Unfair Trade Practices Cases Against Chesapeake, Anadarko On Drilling Royalties, Payments

[Posted: March 15, 2019]


3/18/2019

Go To Preceding Article     Go To Next Article

Return to This PA Environment Digest's Main Page