Court: Injection Well Developer Does Not Need To Wait To Challenge A Local Zoning Decision Until It Has Permits For The Well
|
On March 8, Commonwealth Court issued a ruling that Penneco Environmental Solutions, LLC did not have to wait until it had state and federal permits in hand for a proposed drilling waste injection disposal well before challenging a ruling by Plum Borough’s Zoning Hearing Board against its project in Allegheny County. Click Here for a copy of the ruling. Related Story: [Posted: March 15, 2019] |
3/18/2019 |
Go To Preceding Article Go To Next Article |