Court: Injection Well Developer Does Not Need To Wait To Challenge A Local Zoning Decision Until It Has Permits For The Well

On March 8, Commonwealth Court issued a ruling that Penneco Environmental Solutions, LLC did not have to wait until it had state and federal permits in hand for a proposed drilling waste injection disposal well before challenging a ruling by Plum Borough’s Zoning Hearing Board against its project in Allegheny County.

Click Here for a copy of the ruling.