DEP Orders Sunoco To Cover Exposed Natural Gas Liquids, Other Petroleum Pipelines At 43 Locations Across The State
Photo

On September 11, Department of Environmental Protection ordered Sunoco Pipeline, LP, an Energy Transfer Partners-related company, to cover exposed pipelines at 43 locations across the state.

For security purposes, the Public Utility Confidential Security Information Disclosure Protection Act prohibits state agencies from releasing the locations of the exposed pipelines.

Following the discovery of an exposed pipeline in June, the Public Utility Commission requested that Sunoco identify any additional exposed pipelines and notify both DEP and PUC.

In total, portions of Sunoco’s pipeline network located throughout the Commonwealth are exposed at 43 locations. The exposed pipeline at 42 of those locations is transporting refined petroleum products. The remaining exposed pipeline is transporting natural gas liquids.

The exposed pipelines are not located at ongoing construction areas.

Of the 43 locations, 10 do not require a permit from DEP to address the exposed pipelines due to their location in upland areas. Remediation action is in progress at 10 sites and about to commence at four additional sites.

Sunoco has submitted permit applications that are under DEP review for 10 sites and plans to submit applications at nine additional sites.

“Pipelines can become exposed over time due to erosion in stream channels or due to their position in the ground, as many were constructed before there were standards on how deep they should be buried. These identified pipelines are now exposed to weather, flooding, and vandalism, which can result in a failure of the pipeline and subsequent impacts to our waterways, so it’s critical that Sunoco addresses them immediately,” said DEP Secretary Patrick McDonnell. “DEP is committed to enforcing our regulations and laws to protect our environment.”

Under DEP’s Chapter 105 regulations pertaining to Dam Safety and Waterway Management, “Pipelines under stream beds shall be located such that there will be a minimum of 3 feet of cover between the top of the pipe or encasement and the lowest point in the stream bed; provided, that if the pipeline is in rock, it shall have the depth of granular soil plus six inches for cover, but never less than one foot of total cover.”

According to the order, Sunoco has 30 days to apply for all needed permits on remaining sites and once appropriate permits and approvals are obtained, will have 60 days to bury all exposed pipelines to the appropriate amount of cover and then fully stabilize and restore the site.

Visit DEP’s Pennsylvania Pipeline Portal webpage for more information on pipeline-related actions.

(Photo: A new Energy Transfer Partners/Sunoco natural pipeline exploded in Beaver county in September, 2018.)

NewsClips:

Anya Litvak: DEP Says Energy Transfer Partners Misrepresented The New Revolution Pipeline That Exploded In Beaver County

DEP Orders Sunoco To Cover Exposed Pipelines In 43 Locations

Sinkhole Develops Over Pipeline In Middletown Township Park

New Sinkhole Opens Up Along Mariner East 2 Pipeline In Delaware County

PUC Says No Leak Or Damage To Mariner East 2 Pipeline In Delaware County After Latest Sinkhole

Mariner East Pipeline Foes Hold Rally At Latest Sinkhole Site In Delaware County

Sunoco Mariner East 2 Pipeline Gets Criticism, Support During Twin Valley Middle School Forum

Court: Sen. Dinniman Lacks Legal Standing To Challenge Mariner East Pipelines

Maykuth: Court: Sen. Dinniman Doesn’t Have Legal Standing To Block Sunoco’s Mariner East Pipeline Construction

Mariner East 1 Pipeline Shut Down For Upgrades At Natural Gas Processing Plant In Washington County

Northampton County Town Taking Action To Protect The Appalachian Trail From Pipelines, Cell Towers

Penn State Harrisburg Students Evacuated After Gas Line Struck

Reuters;: U.S. Court Says PennEast Pipeline Cannot Condemn NJ State Lands

Phillips: Federal Appeals Court Strikes Blow To PennEast Pipeline Project Over Condemning NJ State Land

Related Articles:

DEP Issues Sunoco $319,461 In Penalties For Mariner East 2 Pipeline Construction Violations In 2017, 2018; Fines Now Total $13 Million+

How Long Must The Public Wait For Action On Bipartisan Pipeline Safety Bills? New Pipeline Bill Introduced

Briefing: Good, Bad & Ugly Environment & Energy Bills In The PA House, Senate

PUC Pipeline Safety Division Working To Investigate Beaver County Pipeline Explosion

Related Articles This Week:

Earthworks’ New Report, Interactive Map Tracks Disposal Of 380 Million Barrels Of PA Oil & Gas Drilling Wastewater, Including Road Dumping

PUC Investigating Subsidence Involving Several Pipelines Near Site Of Sunoco Mariner East 2 Pipeline Construction In Delaware County

Court: Sen. Dinniman Did Not Have Standing To Bring A Complaint To PUC Over Mariner East Pipeline Construction Failures

Op-Ed: Pennsylvanians Have Landmark Opportunity To Strengthen Pipeline Safety Rules - Clean Air Council [Deadline was Sept. 11]

[Posted: September 11, 2019]


9/16/2019

Go To Preceding Article     Go To Next Article

Return to This PA Environment Digest's Main Page